| Table 4-02.1 . Compact Impact Capital Improvement Projects (P.L. 104-134), Guam FY 1999 to FY 2003 | ||||
| Grant Year | Agency | Project | Total Grant | |
| FY 2003 | DOE | School Repair and Equipment | 700,000 | |
| DOE | Match for FEMA Category E Projects | 300,000 | ||
| DPW | School Buses | 1,500,000 | ||
| GFD | Fire Trucks (project combined with 2002 funds) | 638,000 | ||
| GMHA | Facility Repair and Equipment | 1,355,000 | ||
| GPD | Police Vehicles | 1,080,000 | ||
| Subtotal | $5,573,000 | |||
| FY 2002 | DPW | Elevator and Air Conditioners at DMHSA | 200,000 | |
| DPW | School Buses | 1,300,000 | ||
| DPW | Agana Heights Gym Resurfacing | 28,750 | ||
| DPW | Road Projects | 2,749,000 | ||
| DPW | DOE Water Tanks | 1,000,000 | ||
| DPW | Tumon Police Precinct Supplement | 90,000 | ||
| GFD | Ambulances | 781,000 | ||
| GFD | Fire Trucks | 112,000 | ||
| DOC | Fire Alarm and Sprinkler System | 119,250 | ||
| Subtotal | $6,380,000 | |||
| FY 2001 | DPW | Road Improvement | 6,800,000 | |
| DPW | Library Renovation and Repair | 100,000 | ||
| GFD | Emergency Vehicle Repair | 75,000 | ||
| GFD | Ambulances | 219,000 | ||
| GMH | Equipment Radiology/Orthopedic | 1,125,000 | ||
| GWA | Water Meters | 750,000 | ||
| GWA | Waterline Replacement | 500,000 | ||
| Subtotal | $9,569,000 | |||
| FY 2000 | DPW | Road Projects Phase 1 | 1,950,000 | |
| GMH | Equipment | 2,000,000 | ||
| GMH | Equipment Radiology/Orthopedic | 575,000 | ||
| GWA | Vehicle and Equipment Project | 1,455,000 | ||
| GWA | Water Project Tract 10432 and 10433 | 850,000 | ||
| GWA | Waterline Extension Capital Equipment | 500,000 | ||
| GWA | Pipes and Valves | 250,000 | ||
| Subtotal | $7,580,000 | |||
| FY 1999 | DOA | Financial Management System Phase II | 2,150,000 | |
| DOA/BOP | Y2K Compliance Project | 350,000 | ||
| DPW | Windward Hills Waterline | 700,000 | ||
| DPW | Road Projects | 510,000 | ||
| GFD | Ambulances | 750,000 | ||
| GWA | Vehicle and Equipment Project | 45,000 | ||
| KGTF | Tower Project | 75,000 | ||
| Subtotal | $4,580,000 | |||
| Source: Bureau of Budget and Management Research | ||||
| Table 4-02.2 . Compact Impact Capital Improvement Projects (P.L. 104-134), Guam: FY 1996 to FY 1998 | ||||
| (continued) | ||||
| Grant Year | Agency | Project | Total Grant | |
| FY 1998 | DOA | Financial Management System | 1,800,000 | |
| DPW | Agat Multi-purpose Gymnasium | 100,000 | ||
| DPW | Yigo Secondary Road Project | 300,000 | ||
| DPW | Yigo Multi-purpose Gymnasium | 1,300,000 | ||
| DPW | Tumon Police Precinct Supplement | 230,000 | ||
| DPW | Piti Asbestos Removal | 150,000 | ||
| GWA | Chalan LaChance Water Distribution | 700,000 | ||
| Subtotal | $4,580,000 | |||
| FY 1997 | DPW | Tumon Police Precinct | 650,000 | |
| DPW | Agat Multi-purpose Gymnasium | 100,000 | ||
| GWA | Mataguac Water Distribution | 890,000 | ||
| GWA | Lupog Water Project | 340,000 | ||
| GWA | Chalan Pago Sewer Project | 2,600,000 | ||
| Subtotal | $4,580,000 | |||
| FY 1996 | DPW | Adelup/RJB Complex and Government House | 300,000 | |
| DPW | Talofofo Multi-purpose Gymnasium | 900,000 | ||
| DPW | Yona Multi-purpose Gymnasium | 900,000 | ||
| DPW | Yigo Secondary Road Project | 700,000 | ||
| DPW | Agat Multi-purpose Gymnasium | 750,000 | ||
| GMH | Equipment | 420,000 | ||
| GWA | Anoa Point Subdivision | 600,000 | ||
| GWA | Mataguac Water Distribution | 10,000 | ||
| Subtotal | $4,580,000 | |||
| GRAND TOTAL CIP FUNDS | $47,422,000 | |||
| Source: Bureau of Budget and Management Research | ||||